Substation Scout

Pinewood- St Johns 115kV

PJM queue ID AH1-454 Terminal status

Queue IDAH1-454
Project namePinewood- St Johns 115kV
Status (as published)Withdrawn
SubstationPinewood- St Johns
Point of interconnectionPinewood- St Johns 115kV
CountyCaroline
StateVA
Voltage115 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity100
Mfo100
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.