East Palmerton-Harwood 230 kV

PJM queue ID AH1-448 Terminal status

Queue IDAH1-448
Project nameEast Palmerton-Harwood 230 kV
Status (as published)Withdrawn
SubstationEast Palmerton-Harwood
Point of interconnectionEast Palmerton-Harwood 230 kV
CountyCarbon
StatePA
Voltage230 kV
Capacity180 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy180
Mw Capacity180
Mfo180
Withdrawn Date10/13/2021