Axton – Danville #2 138 kV

PJM queue ID AH1-447 Terminal status

Queue IDAH1-447
Project nameAxton – Danville #2 138 kV
Status (as published)Withdrawn
SubstationAxton – Danville #2
Point of interconnectionAxton – Danville #2 138 kV
CountyPittsylvania
StateVA
Voltage138 kV
Capacity36 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-12-02
Source datasetcycle

Additional filed fields

DeveloperCascade Energy Storage, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageAPPLICATION REVIEW
Mw Energy60.0
Mw Capacity36.0
Mfo60.0
Submitted Date9/10/2021
Withdrawn Date3/20/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/25/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.