Substation Scout

Gilboa-Jones Branch 138 kV V

PJM queue ID AH1-426A Terminal status

Queue IDAH1-426A
Project nameGilboa-Jones Branch 138 kV V
Status (as published)Withdrawn
SubstationGilboa-Jones Branch V
Point of interconnectionGilboa-Jones Branch 138 kV V
CountyNicholas
StateWV
Voltage138 kV
Capacity32.3 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-12-31
Source datasetcycle

Additional filed fields

DeveloperNicholas County Solar Project, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy32.3
Mw Capacity32.3
Mfo96.9
Submitted Date9/11/2021
Withdrawn Date12/1/2025
Withdrawn RemarksCIW
Last Updated10/30/2025