Thompson 34.5 kV II

PJM queue ID AH1-419 Terminal status

Queue IDAH1-419
Project nameThompson 34.5 kV II
Status (as published)Withdrawn
SubstationThompson II
Point of interconnectionThompson 34.5 kV II
CountySusquehanna
StatePA
Voltage34.5 kV
Capacity20 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2025-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.