Shelocta 115kV

PJM queue ID AH1-403 Terminal status

Queue IDAH1-403
Project nameShelocta 115kV
Status (as published)Withdrawn
SubstationShelocta
Point of interconnectionShelocta 115kV
CountyIndiana
StatePA
Voltage115 kV
Capacity29.1 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity29.1
Mfo85
Withdrawn Date8/21/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.