Substation Scout

Mainesburg 115 kV

PJM queue ID AH1-394 Terminal status

Queue IDAH1-394
Project nameMainesburg 115 kV
Status (as published)Withdrawn
SubstationMainesburg
Point of interconnectionMainesburg 115 kV
CountyTioga
StatePA
Voltage115 kV
Capacity4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10.5
Mw Capacity3.99
Mfo10.5
Withdrawn Date2/2/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.