Substation Scout

Cobbs Creek- James River 115kV

PJM queue ID AH1-375 Terminal status

Queue IDAH1-375
Project nameCobbs Creek- James River 115kV
Status (as published)Withdrawn
SubstationCobbs Creek- James River
Point of interconnectionCobbs Creek- James River 115kV
CountyFluvanna
StateVA
Voltage115 kV
Capacity36 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity36
Mfo60
Withdrawn Date11/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.