Kings Creek 138kV

PJM queue ID AH1-356 Terminal status

Queue IDAH1-356
Project nameKings Creek 138kV
Status (as published)Withdrawn
SubstationKings Creek
Point of interconnectionKings Creek 138kV
CountySomerset
StateMD
Voltage138 kV
Capacity30 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-09-30
Source datasetcycle

Additional filed fields

DeveloperGreat Bay Solar II, LLC
Transmission OwnerDPL
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy30.0
Mw Capacity30.0
Mfo30.0
Submitted Date9/10/2021
Withdrawn Date3/14/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025