Substation Scout

Preston County Solar Project

PJM queue ID AH1-340 Terminal status

Queue IDAH1-340
Project namePreston County Solar Project
Status (as published)Withdrawn
SubstationCheat Lake-Ruthbelle
Point of interconnectionCheat Lake-Ruthbelle 138 kV
CountyPreston
StateWV
Voltage138 kV
Capacity29.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-31
Source datasetcycle

Additional filed fields

DeveloperRockville Solar LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy48.89
Mw Capacity29.33
Mfo48.89
Submitted Date9/10/2021
Withdrawn Date11/13/2025
Withdrawn RemarksCIW
Last Updated10/7/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.