Kirk 138 kV

PJM queue ID AH1-325 Terminal status

Queue IDAH1-325
Project nameKirk 138 kV
Status (as published)Withdrawn
SubstationKirk
Point of interconnectionKirk 138 kV
CountyLicking
StateOH
Voltage138 kV
Capacity50 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-12-31
Source datasetcycle

Additional filed fields

DeveloperInvenergy Storage Development LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy50.0
Mw Capacity50.0
Mfo50.0
Submitted Date9/9/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025