Substation Scout

Blue Jacket - Kirby 138 kV

PJM queue ID AH1-320 Terminal status

Queue IDAH1-320
Project nameBlue Jacket - Kirby 138 kV
Status (as published)Withdrawn
SubstationBlue Jacket - Kirby
Point of interconnectionBlue Jacket - Kirby 138 kV
CountyLogan
StateOH
Voltage138 kV
Capacity69 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-12-31
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperInvenergy Storage Development LLC
Transmission OwnerDayton
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy69.0
Mw Capacity69.0
Mfo275.55
Submitted Date9/10/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.