Substation Scout

Sloopy Storage

PJM queue ID AH1-319 Terminal status

Queue IDAH1-319
Project nameSloopy Storage
Status (as published)Withdrawn
SubstationEast Springfield-London II
Point of interconnectionEast Springfield-London 138 kV II
CountyClark
StateOH
Voltage138 kV
Capacity54 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-12-31
Source datasetcycle

Additional filed fields

DeveloperInvenergy Storage Development LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy54.0
Mw Capacity54.0
Mfo54.0
Submitted Date9/10/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025