Substation Scout

Greene - Beatty 345 kV

PJM queue ID AH1-317 Terminal status

Queue IDAH1-317
Project nameGreene - Beatty 345 kV
Status (as published)Withdrawn
SubstationGreene - Beatty
Point of interconnectionGreene - Beatty 345 kV
CountyMadison
StateOH
Voltage345 kV
Capacity120 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity120
Mfo200
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.