Nittany North Solar

PJM queue ID AH1-313 Terminal status

Queue IDAH1-313
Project nameNittany North Solar
Status (as published)Withdrawn
SubstationMoshannon-Milesburg VII
Point of interconnectionMoshannon-Milesburg 230 kV VII
CountyCentre
StatePA
Voltage230 kV
Capacity60 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Additional filed fields

DeveloperInvenergy Solar Project Development LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy100.0
Mw Capacity60.0
Mfo100.0
Submitted Date9/10/2021
Withdrawn Date12/3/2025
Withdrawn RemarksCMN