Substation Scout

Kewanee - E.D. Edwards 138 kV

PJM queue ID AH1-297 Terminal status

Queue IDAH1-297
Project nameKewanee - E.D. Edwards 138 kV
Status (as published)Withdrawn
SubstationKewanee - E.D. Edwards
Point of interconnectionKewanee - E.D. Edwards 138 kV
CountyStark
StateIL
Voltage138 kV
Capacity26 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2025-12-31
Source datasetcycle

Additional filed fields

DeveloperInvenergy Wind Development LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy200.0
Mw Capacity26.0
Mfo200.0
Submitted Date9/10/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025