Winslow Landfill Solar Farm
PJM queue ID AH1-265 Terminal status
| Queue ID | AH1-265 |
|---|---|
| Project name | Winslow Landfill Solar Farm |
| Status (as published) | Withdrawn |
| Substation | Winslow - Monroe |
| Point of interconnection | Winslow - Monroe 69kV |
| County | Camden |
| State | NJ |
| Voltage | 69 kV |
| Capacity | 12.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-03-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Winslow LF Solar Farm, LLC |
|---|---|
| Transmission Owner | AEC |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 29.4 |
| Mw Capacity | 12.35 |
| Mfo | 29.4 |
| Submitted Date | 9/10/2021 |
| Withdrawn Date | 12/2/2025 |
| Withdrawn Remarks | CIW |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.