Pulaski Energy Storage

PJM queue ID AH1-261 Terminal status

Queue IDAH1-261
Project namePulaski Energy Storage
Status (as published)Withdrawn
SubstationNortheast - Riverside
Point of interconnectionNortheast - Riverside 230 kV
CountyBaltimore County
StateMD
Voltage230 kV
Capacity135 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-01
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 135 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperPulaski Energy Storage LLC
Transmission OwnerBGE
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy135.0
Mw Capacity135.0
Mfo135.0
Submitted Date9/10/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCMN
Last Updated12/23/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.