Substation Scout

Kidds Store - Fork Union 115 kV II

PJM queue ID AH1-217 Terminal status

Queue IDAH1-217
Project nameKidds Store - Fork Union 115 kV II
Status (as published)Withdrawn
SubstationKidds Store - Fork Union II
Point of interconnectionKidds Store - Fork Union 115 kV II
CountyFluvanna
StateVA
Voltage115 kV
Capacity34.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-11-30
Source datasetcycle

Additional filed fields

DeveloperMountain Pine Kidds Store LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy57.0
Mw Capacity34.2
Mfo57.0
Submitted Date9/9/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.