Substation Scout

Allegheny-New Baltimore 115kV

PJM queue ID AH1-205 Terminal status

Queue IDAH1-205
Project nameAllegheny-New Baltimore 115kV
Status (as published)Withdrawn
SubstationAllegheny-New Baltimore
Point of interconnectionAllegheny-New Baltimore 115kV
CountySomerset
StatePA
Voltage115 kV
Capacity16 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-01
Source datasetcycle

Additional filed fields

DeveloperMango Solar LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy0.0
Mw Capacity16.0
Mfo40.0
Submitted Date9/3/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.