ASD Woodbury PA2 Solar I
PJM queue ID AH1-162 Terminal status
| Queue ID | AH1-162 |
|---|---|
| Project name | ASD Woodbury PA2 Solar I |
| Status (as published) | Withdrawn |
| Substation | Curryville-RKB-Yellow Creek |
| Point of interconnection | Curryville-RKB-Yellow Creek 23 kV |
| County | Bedford |
| State | PA |
| Voltage | 23 kV |
| Capacity | 11 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2023-11-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | ASD Woodbury PA2 Solar I LLC |
|---|---|
| Transmission Owner | PENELEC |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | PHASE 1 |
| Mw Energy | 16.0 |
| Mw Capacity | 11.0 |
| Mfo | 16.0 |
| Submitted Date | 8/31/2021 |
| Withdrawn Date | 7/7/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |
| Last Updated | 10/31/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.