Vasco 138 kV

PJM queue ID AH1-140 Terminal status

Queue IDAH1-140
Project nameVasco 138 kV
Status (as published)Withdrawn
SubstationVasco
Point of interconnectionVasco 138 kV
CountyWestmoreland
StatePA
Voltage138 kV
Capacity115 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-12-31
Source datasetcycle

Additional filed fields

DeveloperRed Stone Renewables, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy150.0
Mw Capacity115.0
Mfo150.0
Submitted Date7/30/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW
Last Updated10/30/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.