Dowling 138 kV II

PJM queue ID AH1-122 Terminal status

Queue IDAH1-122
Project nameDowling 138 kV II
Status (as published)Withdrawn
SubstationDowling II
Point of interconnectionDowling 138 kV II
CountyWood
StateOH
Voltage138 kV
Capacity9.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy22
Mw Capacity9.24
Mfo75
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.