Substation Scout

Newville 12 kV II

PJM queue ID AH1-110 Terminal status

Queue IDAH1-110
Project nameNewville 12 kV II
Status (as published)Withdrawn
SubstationNewville II
Point of interconnectionNewville 12 kV II
CountyCumberland
StatePA
Voltage12 kV
Capacity3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-07-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity3
Mfo5
Withdrawn Date8/7/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.