Substation Scout

Wolf Glade-West Carroll 138 kV

PJM queue ID AH1-098 Terminal status

Queue IDAH1-098
Project nameWolf Glade-West Carroll 138 kV
Status (as published)Withdrawn
SubstationWolf Glade-West Carroll
Point of interconnectionWolf Glade-West Carroll 138 kV
CountyCarroll
StateVA
Voltage138 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 24 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperPine Branch Solar, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy40.0
Mw Capacity24.0
Mfo40.0
Submitted Date7/30/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated7/2/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.