PJM queue ID AH1-086 Terminal status

Queue IDAH1-086
Project nameSummersweet Energy Center, LLC
Status (as published)Withdrawn
SubstationMorrisville
Point of interconnectionMorrisville 230kV
CountyFauquier
StateVA
Voltage230 kV
Capacity90 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-12-01
Source datasetcycle

Additional filed fields

DeveloperSummersweet Energy Center, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy90.0
Mw Capacity90.0
Mfo90.0
Submitted Date7/30/2021
Withdrawn Date11/26/2025
Withdrawn RemarksCIW
Last Updated10/10/2025