Substation Scout

Knob Lick 69kV

PJM queue ID AH1-082 Terminal status

Queue IDAH1-082
Project nameKnob Lick 69kV
Status (as published)Withdrawn
SubstationKnob Lick
Point of interconnectionKnob Lick 69kV
CountyMetcalfe
StateKY
Voltage69 kV
Capacity26.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-20
Source datasetcycle

Additional filed fields

DeveloperWildrye Solar LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy44.0
Mw Capacity26.4
Mfo104.0
Submitted Date7/30/2021
Withdrawn Date5/5/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025