Substation Scout

Galion 138 kV IV

PJM queue ID AH1-058 Terminal status

Queue IDAH1-058
Project nameGalion 138 kV IV
Status (as published)Withdrawn
SubstationGalion IV
Point of interconnectionGalion 138 kV IV
CountyMorrow
StateOH
Voltage138 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy40
Mw Capacity24
Mfo204
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.