Substation Scout

Stony Run Solar Project, LLC

PJM queue ID AH1-042 Terminal status

Queue IDAH1-042
Project nameStony Run Solar Project, LLC
Status (as published)Withdrawn
SubstationProvidence Forge-Turner
Point of interconnectionProvidence Forge-Turner 115kV
CountyCharles City
StateVA
Voltage115 kV
Capacity99.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-09-30
Source datasetcycle

Additional filed fields

DeveloperStony Run Solar Project, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy154.0
Mw Capacity99.9
Mfo154.0
Submitted Date6/25/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.