Plymouth 34.5 kV
PJM queue ID AH1-035 Terminal status
| Queue ID | AH1-035 |
|---|---|
| Project name | Plymouth 34.5 kV |
| Status (as published) | Withdrawn |
| Substation | Plymouth |
| Point of interconnection | Plymouth 34.5 kV |
| County | Washington |
| State | NC |
| Voltage | 34.5 kV |
| Capacity | 13.5 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-12-31 |
| Source dataset | cycle |
Additional filed fields
| Developer | Park Solar, LLC |
|---|---|
| Transmission Owner | Dominion |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 20.0 |
| Mw Capacity | 13.5 |
| Mfo | 20.0 |
| Submitted Date | 6/14/2021 |
| Withdrawn Date | 12/2/2025 |
| Withdrawn Remarks | CIW |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.