Substation Scout

Garrard 345 kV

PJM queue ID AG2-687 Terminal status

Queue IDAG2-687
Project nameGarrard 345 kV
Status (as published)Withdrawn
SubstationGarrard
Point of interconnectionGarrard 345 kV
CountyGarrard
StateKY
Voltage345 kV
Capacity129 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy215
Mw Capacity129
Mfo215
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.