Substation Scout

Kanawha River - Carbondale 138 kV

PJM queue ID AG2-656 Terminal status

Queue IDAG2-656
Project nameKanawha River - Carbondale 138 kV
Status (as published)Withdrawn
SubstationKanawha River - Carbondale
Point of interconnectionKanawha River - Carbondale 138 kV
CountyKanawha
StateWV
Voltage138 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity60
Mfo100
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.