Substation Scout

Palmer Springs 115 kV

PJM queue ID AG2-641 Terminal status

Queue IDAG2-641
Project namePalmer Springs 115 kV
Status (as published)Withdrawn
SubstationPalmer Springs
Point of interconnectionPalmer Springs 115 kV
CountyMecklenburg
StateVA
Voltage115 kV
Capacity48 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-04-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity48
Mfo80
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.