Boydton Plank Road 115 kV
PJM queue ID AG2-631 Terminal status
| Queue ID | AG2-631 |
|---|---|
| Project name | Boydton Plank Road 115 kV |
| Status (as published) | Withdrawn |
| Substation | Boydton Plank Road |
| Point of interconnection | Boydton Plank Road 115 kV |
| County | Mecklenburg |
| State | VA |
| Voltage | 115 kV |
| Capacity | 90 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2025-04-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | ACE Development Company, LLC |
|---|---|
| Transmission Owner | Dominion |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | PHASE 1 |
| Mw Energy | 150.0 |
| Mw Capacity | 90.0 |
| Mfo | 150.0 |
| Submitted Date | 3/31/2021 |
| Withdrawn Date | 7/3/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |
| Last Updated | 10/31/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.