Substation Scout

Gold 12.5 kV

PJM queue ID AG2-610 Terminal status

Queue IDAG2-610
Project nameGold 12.5 kV
Status (as published)Withdrawn
SubstationGold
Point of interconnectionGold 12.5 kV
CountyPotter
StatePA
Voltage12.5 kV
Capacity3.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy4.998
Mw Capacity3.9
Mfo4.998
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.