Furnace Brook-Warren 34.5 kV

PJM queue ID AG2-599 Terminal status

Queue IDAG2-599
Project nameFurnace Brook-Warren 34.5 kV
Status (as published)Withdrawn
SubstationFurnace Brook-Warren
Point of interconnectionFurnace Brook-Warren 34.5 kV
CountyWarren
StateNJ
Voltage34.5 kV
Capacity8.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-04-30
Source datasetcycle

Additional filed fields

DeveloperOxford Textile Solar Farm, LLC
Transmission OwnerJCPL
Project TypeGeneration Interconnection
CycleTC2
StageAPPLICATION REVIEW
Mw Energy19.6
Mw Capacity8.232
Mfo19.6
Submitted Date3/31/2021
Withdrawn Date2/18/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated2/18/2025