LaRue - North Waldo 138 kV
PJM queue ID AG2-595 Terminal status
| Queue ID | AG2-595 |
|---|---|
| Project name | LaRue - North Waldo 138 kV |
| Status (as published) | Withdrawn |
| Substation | LaRue - North Waldo |
| Point of interconnection | LaRue - North Waldo 138 kV |
| County | Marion |
| State | OH |
| Voltage | 138 kV |
| Capacity | 6.5 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2024-06-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Riverlake Energy, LLC |
|---|---|
| Transmission Owner | AEP |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | PHASE 1 |
| Mw Energy | 65.0 |
| Mw Capacity | 6.5 |
| Mfo | 65.0 |
| Submitted Date | 3/31/2021 |
| Withdrawn Date | 7/3/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |
| Last Updated | 10/31/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.