Substation Scout

Bluebell-Sancap Tap 69 kV

PJM queue ID AG2-591 Terminal status

Queue IDAG2-591
Project nameBluebell-Sancap Tap 69 kV
Status (as published)Withdrawn
SubstationBluebell-Sancap Tap
Point of interconnectionBluebell-Sancap Tap 69 kV
CountyMahoning
StateOH
Voltage69 kV
Capacity36.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy61
Mw Capacity36.6
Mfo61
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.