Shingletown-Lewistown 230 kV
PJM queue ID AG2-590 Terminal status
| Queue ID | AG2-590 |
|---|---|
| Project name | Shingletown-Lewistown 230 kV |
| Status (as published) | Withdrawn |
| Substation | Shingletown-Lewistown |
| Point of interconnection | Shingletown-Lewistown 230 kV |
| County | Huntingdon |
| State | PA |
| Voltage | 230 kV |
| Capacity | 22.9 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2024-06-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | North Corners Energy, LLC |
|---|---|
| Transmission Owner | PENELEC |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | APPLICATION REVIEW |
| Mw Energy | 38.2 |
| Mw Capacity | 22.9 |
| Mfo | 92.1 |
| Submitted Date | 3/31/2021 |
| Withdrawn Date | 1/30/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |