Shingletown-Lewistown 230 kV

PJM queue ID AG2-590 Terminal status

Queue IDAG2-590
Project nameShingletown-Lewistown 230 kV
Status (as published)Withdrawn
SubstationShingletown-Lewistown
Point of interconnectionShingletown-Lewistown 230 kV
CountyHuntingdon
StatePA
Voltage230 kV
Capacity22.9 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-06-01
Source datasetcycle

Additional filed fields

DeveloperNorth Corners Energy, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageAPPLICATION REVIEW
Mw Energy38.2
Mw Capacity22.9
Mfo92.1
Submitted Date3/31/2021
Withdrawn Date1/30/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/30/2025