Substation Scout

Double Toll Gate - Meadowbrook 138 kV

PJM queue ID AG2-584 Terminal status

Queue IDAG2-584
Project nameDouble Toll Gate - Meadowbrook 138 kV
Status (as published)Withdrawn
SubstationDouble Toll Gate - Meadowbrook
Point of interconnectionDouble Toll Gate - Meadowbrook 138 kV
CountyFrederick
StateVA
Voltage138 kV
Capacity46.8 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy90
Mw Capacity46.8
Mfo90
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.