PJM queue ID AG2-581 Terminal status

Queue IDAG2-581
Project nameRawlings - Unity 500 kV
Status (as published)Withdrawn
SubstationRawlings - Unity
Point of interconnectionRawlings - Unity 500 kV
CountyBrunswick
StateVA
Voltage500 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 90 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy150.0
Mw Capacity90.0
Mfo150.0
Submitted Date1/29/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated3/20/2026