PJM queue ID AG2-566 Terminal status

Queue IDAG2-566
Project nameBriery - Finneywood 230 kV
Status (as published)Withdrawn
SubstationBriery - Finneywood
Point of interconnectionBriery - Finneywood 230 kV
CountyPrince Edward
StateVA
Voltage230 kV
Capacity12 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 12 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperGabriel Storage, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy30.0
Mw Capacity12.0
Mfo110.0
Submitted Date3/31/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated12/27/2025