Substation Scout

Clubhouse - Jarratt 115 kV

PJM queue ID AG2-540 Terminal status

Queue IDAG2-540
Project nameClubhouse - Jarratt 115 kV
Status (as published)Withdrawn
SubstationClubhouse - Jarratt
Point of interconnectionClubhouse - Jarratt 115 kV
CountyGreensville
StateVA
Voltage115 kV
Capacity48 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-06-03
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity48
Mfo80
Withdrawn Date12/10/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.