Substation Scout

Pohatcong-Newburgh Tap 34.5 kV

PJM queue ID AG2-532 Terminal status

Queue IDAG2-532
Project namePohatcong-Newburgh Tap 34.5 kV
Status (as published)Withdrawn
SubstationPohatcong-Newburgh Tap
Point of interconnectionPohatcong-Newburgh Tap 34.5 kV
CountyWarren
StateNJ
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-31
Source datasetcycle

Additional filed fields

DeveloperV20 Mansfield LLC
Transmission OwnerJCPL
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy20.0
Mw Capacity0.0
Mfo20.0
Submitted Date3/31/2021
Withdrawn Date12/4/2025
Withdrawn RemarksCMN
Last Updated11/27/2025