LaSalle Station - Mazon 138 kV
PJM queue ID AG2-524 Terminal status
| Queue ID | AG2-524 |
|---|---|
| Project name | LaSalle Station - Mazon 138 kV |
| Status (as published) | Withdrawn |
| Substation | LaSalle Station - Mazon |
| Point of interconnection | LaSalle Station - Mazon 138 kV |
| County | Grundy |
| State | IL |
| Voltage | 138 kV |
| Capacity | 110 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2028-06-30 |
| Source dataset | cycle |
Tracked changes
1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Terminal status | 110 | Active → Withdrawn |
Additional filed fields
| Developer | Hog Run Solar, LLC |
|---|---|
| Transmission Owner | ComEd |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 2 |
| Mw Energy | 110.0 |
| Mw Capacity | 110.0 |
| Mfo | 110.0 |
| Submitted Date | 3/31/2021 |
| Withdrawn Date | 9/30/2026 |
| Withdrawn Remarks | CIW |
| Last Updated | 3/16/2026 |