Bakers Pond 115 kV
PJM queue ID AG2-523 Terminal status
| Queue ID | AG2-523 |
|---|---|
| Project name | Bakers Pond 115 kV |
| Status (as published) | Withdrawn |
| Substation | Bakers Pond |
| Point of interconnection | Bakers Pond 115 kV |
| County | Prince George |
| State | VA |
| Voltage | 115 kV |
| Capacity | 100 MW |
| Resource (as published) | Solar; Storage |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | Not reported |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 100 |
| Mw Capacity | 100 |
| Mfo | 100 |
| Withdrawn Date | 3/31/2022 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.