Midway 345 kV III
PJM queue ID AG2-515 Terminal status
| Queue ID | AG2-515 |
|---|---|
| Project name | Midway 345 kV III |
| Status (as published) | Withdrawn |
| Substation | Midway III |
| Point of interconnection | Midway 345 kV III |
| County | Lucas |
| State | OH |
| Voltage | 345 kV |
| Capacity | 60 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-07-31 |
| Source dataset | cycle |
Additional filed fields
| Developer | Starling Solar Project, LLC |
|---|---|
| Transmission Owner | ATSI |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 100.0 |
| Mw Capacity | 60.0 |
| Mfo | 100.0 |
| Submitted Date | 3/31/2021 |
| Withdrawn Date | 11/28/2025 |
| Withdrawn Remarks | CIW |
| Last Updated | 11/19/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.