Substation Scout

Midway 345 kV II

PJM queue ID AG2-514 Terminal status

Queue IDAG2-514
Project nameMidway 345 kV II
Status (as published)Withdrawn
SubstationMidway II
Point of interconnectionMidway 345 kV II
CountyHenry
StateOH
Voltage345 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity90
Mfo150
Withdrawn Date12/13/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.