Adams 138 kV

PJM queue ID AG2-503 Terminal status

Queue IDAG2-503
Project nameAdams 138 kV
Status (as published)Withdrawn
SubstationAdams
Point of interconnectionAdams 138 kV
CountyAdams
StateOH
Voltage138 kV
Capacity5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity5
Mfo49.9
Withdrawn Date12/18/2024