Meadow Lake 345 kV

PJM queue ID AG2-491

Queue IDAG2-491
Project nameMeadow Lake 345 kV
Status (as published)Active
SubstationMeadow Lake
Point of interconnectionMeadow Lake 345 kV
CountyWhite
StateIN
Voltage345 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperBlack Prairie Solar Park II LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy100.0
Mw Capacity60.0
Mfo100.0
Submitted Date3/31/2021
Last Updated5/14/2026