Substation Scout

Meadow Lake 345 kV

PJM queue ID AG2-491 Terminal status

Queue IDAG2-491
Project nameMeadow Lake 345 kV
Status (as published)Withdrawn
SubstationMeadow Lake
Point of interconnectionMeadow Lake 345 kV
CountyWhite
StateIN
Voltage345 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-04-01
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 60 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperBlack Prairie Solar Park II LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy100.0
Mw Capacity60.0
Mfo100.0
Submitted Date3/31/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated2/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.